Hello,
Does anyone know if there is a form of a "Late Finish" that would be calculated as the latest date an activity can finish without affecting the start date of any of its successor activities? (i.e. Latest Finish where Free Float = 0)
I have fabrication and long lead activities that I do not want to drive any of my construction activities, and would like to give "drop dead" dates to our fabricators.
As a general practice, I filter my fabrication activities for Free Float = 0d to generate a list of fabrication items driving my construction dates. Then I use this list to give a warning that fabrication is slipping.
I would prefer to generate a list of all fabrication activities that shows the finish date that would use up all of that activity's free float.
This question was touched upon in a 2007 post, but I don't see an answer that works for me. http://planningplanet.com/forums/microsoft-project/415942/late-start-free-float
Any other suggestions are appreciated.
Thanks!
Greg