Hi,
Any suggestion on where to find a well-detailed explanation of how the lag between different activities in P6 are scheduled?
I am experiencing some strange behaviors in particular cases, for which I am not able to provide a rational explanation.
e.g. :if I select the successor´s calendar for scheduling the lag between two activities with different calendars, I see that the days are converted any case in hours following the calendar of the predecessor. This seems counter-intuitive to me but I can´t find the setting to change it. I would like to understand if there is a specific reason for this, as I can´t see it myself.