Hi! I assigned some resource for trial, with its "Default Units/ time as 8/d" and then I assigned it to activities. After scheduling, the programme calculates the labour units based on that.
(Pic 1) But then when I change the same resource "Default Units/time as 2/d" and scheduled, it does not recalculate the Labour units.
(Pic 2) I tried doing it with cost, changing it from $2/d to $8/d. And then I Clicked on "Recalculated the cost assignment" and it worked. In pic 2 you can see the Cost changed but labour units did not, even after scheduling.
Any setting or logic I am missing? Also After changing the default currency from AED to USD, it is not changing.