Is it possible to have 2 resourses spending hours from the same budget on an activity?
The case is like this:
- Activity 1 have a budget of 100 hours
- Resource department 1(own manning) have capacity of 30 hours.
- Resource department 1 (hired manning) will be working out the rest of the 70 hours
The capacity of resource 1 (own manning) is not conistent as own manning also is divided on several projects.
Is there a possibility where these 2 different resources spend hours from one common activity budget?