Hi All,
Badly need your advise.
I am trying to copy the updates from 'X' program onto another program 'Y'. X has Y+150 activities.
I did the exporting to excel and imported the relevant activities in to X program. All is find except for a few hundred activities which do not have any WBS assigned. These are being placed outside the WBS under the main program name. In other words these moved out from their respective WBS heads.
I tried changing the name of WBS path in excel but of no help. I am not finding a global change option to make changes to WBS. Please provide your suggestions.
Thanks in advance
Prathy