I'm trying to understand why P6 resource levels over non-working time hours. For example, I have a resource that only works Monday - Friday but when I resource level, it shows as an over-allocation at the weekends where I would have thought it would extend the duration to account for this. I do not have the "Level resources only within activity Total Float" option selected.
Can anyone suggest where I may have a setting wrong - I have been through all the user prefs and cannot see anything to affect it.
Thanks in advance!