Hello, I am trying to close a pfoject in Primavera P6, which has not been completed but has to be closed untimely.
Some activities, which had been planned earlied and which were going to start in the future, never started.
How do I properly close it in Primavera P6?
For example, today is 25 July 2017. Activity A is the latest activity and is planned to start on 1 January 2018 and finish on 1 January 2020.
I have closed the project but the finish date of the project shows 1 Jan 2020. How do I need to deal with unstarted activities? Do I mark them "finished" and put some random date that was before the 25 Jul 2017 or do I just delete unstarted activities so the project finish date is not affected?