Hi everyone,
Whenever I create a reflection of a schedule, all the WBS names inside that schedule will also include the word "Reflection". It is very time consuming to delete the word "Reflection" one by one. Has anyone encounter this issue or have a solution for it?
I'm using R15.2.13
Thank you