MS Projects tells me when I open my planning that:
No calculation can be performed because of a circular relationship. Successors of task 462 refer back to this task (Or as I assume one of its subtasks) or its predecessors.
Now this include quit a lot of possible tasks which may cause this circular relation. Is there a smart way to find them?
Many thanks in advance for any help.
Martin