Dear all,
I just noticed, that there is no such activity field as activity status in Spider. Such field is normally available in other tools.
E.g: In MS Project:
· Complete
· Future Task
· On schedule
· Late
In Primavera
· Not Started
· In Progress
· Complete
I am sure, there is a reason for it, but just wondering how Spider deals with the absence of activity status.
E.g, how would I filter activities, which are “in progress ” ?