The requirement of my one year project is to prepare a report based upon the manhours and Materials. The progresss should be shown based on that only. I have assigned Manhours of and Non material resource into each activity of the project. I need the output from that, Please explain to me to obtain output of Manhours as well as Non material progress updation and results. They also want result in such a way that 40 percent weightage on manhours and 60 percentage based on Material resource progress. If the output can't be shown in primavera tell me how to make that in excel from primavera values. Please help. (Cost calculation is not required).