Hi Planners,
A baseline schedule showing that the start date of the project "milestone task" is not critical "9 days float", some of the succesor tasks has a constraint "start no earlier than". I changed the constraint of those successors to "Must start on" and I got the start date critical. Is there any explanation to this?
Regards,