Dear Construction planner,
Is there soemone there who can confirm the work sequence for activities mentioned in the subject:
AFTER A/G piping installed, the sequence is as follow:
First painting (except the welds)
Second , install heat tracing (if aplicacble).
Third, hydrotest
Fourth, reinstament + final painting.
Final , Insulation.
Is this correct ??? any skilled construction planner out there.
Thanks in advance,
Carmen