Hi Friends,
I have an LOE activity with SS and FF relationship to a set of activities.
There were delays in the activities and the orignal and at completion is now different for the activities as well as the LOE activity now.
The activity % complete is less that Scheduel % complete which is exptected.
But now the current dates have been accepted as new baseline. But even if I save the current project as the baseline, the activity % complete and Schedule % complete are showing different value, for LOE as well as its predecssor activities. Can I fix it?
I want to use the LOE for summary activitiy for reporting and the difference between A%C and S%C as delay in in a group of activities.
Thank you.