Hi
Need your support here.
This is related to Manufacturing planning works.
Activity A - Machining operation - 15 days
Activity B - Machining operation - 10 days
Activity C - MAchining operation - 20 days
Activity D - Machining operation - 25 days
Activity E - Machining operation - 5 days
Activity F - Machining operation - 5 days.
All activites were independent. We are having two resources say LATHE 1 and LATHE 2. Is it possible in Primavera , assigning the resource for the above activities ( either LATHE 1 or LATHE 2 ) will be done automatically depends on the resource loading/activity operation to get better result. (Shortest Project Duration).
Thanks in advance
Ram