Hello Experts,
I will really appreciate if someone can help/guide me with scheduling strategy for the following query:
Question:
I have a project of 270 Villas having different types as follows:
Type 4 = 255
Type 6 = 15
As per client's requirement WBS for construction of villas will be block wise as follows:
BLOCK 1 = 39 Villas
BLOCK 2 = 39 Villas
BLOCK 3 = 39 Villas
BLOCK 4 = 39 Villas
BLOCK 5 = 39 Villas
BLOCK 6 = 39 Villas
BLOCK 7 = 36 Villas
Set of activities for each block will be same as for one villa.
Now the problem is,
1. How i should calculate the duration of my activities for each block?
2. What should be the links of activities?
Hope i have explained good. If further information is required please ask. Thanks in advance for your usual support.