Any suggestions out there on a way to extract the amount of actual bodies I will have on a jobsite after I have all my resource loaded.
I suppose I could export the units out to an excel spreadsheet and get it from there based on my units max per day, and the calendar, but was curious if there was a way to do that in P6.
Thanks in advance.
PS. be gently, I'm not a full time scheduler. What may seem easy to you, is like rocket science to me.