It is easy to output % complete from MS Project however I have not yet managed to find out how to output either:
* Complete through - a value which appears to be only available to the Gantt graphic
* The date circled in the picture below - i.e. where a summary has really got to.
[img]http://i68.tinypic.com/2elgg05.jpg[/img]
These are especially useful when you have a summary task containing front or back end loaded activity so that in the first half of the summary you will have completed 75-90% of the actual work / duration but 75% complete would suggest that you're ahead of the schedule which is only actually half way through.
Any ideas gratefully received! :)
Thanks
Miles