Submitted by Sagar Hassan on Wed, 2016-11-16 11:16
START Date:
September, 2016
- Monitoring & Scheduling Tool : Primavera 6.0 Version 8.2
- Prepared Mobilization Plan & Organization Chart.
- Prepared Project Schedule in (Primavera 6.0 Version 8.2, Microsoft Excel).
- Preparation of Resource Loading.
- To identify the root cause of any delay event and report to Project Manager with recommended corrective action.
- Earned Value Management.
- Generate Monthly, Weekly and Daily Reports.
- Preparation of 2-3-Look Ahead program for weekly and monthly analysis with Bar Chart.
- Actual Men-Hours calculation from Time Sheet.
- Prepared Site Issues Report.
- Prepared others related formats time to time as per requirement.
- Calculate the Budgeted (Plan) Man-hours vs. Actual (Earned) Man-hours.
- Prepared Person on Board & Tool & Plants & Equipment Report.
- Prepared 4-Weeks Look Ahead Schedule (Forecast).
Experience Hours (Planning & Scheduling):
400
Links:
[1] http://www.planningplanet.com/category/project/qatar-metro-project-energy-greengold-blue-line
[2] http://www.planningplanet.com/category/skills-expertise/result-oriented-professional-95-years-industrial-exposure
[3] http://www.planningplanet.com/category/company/concord-electrical-contracting-llc-0
[4] http://www.planningplanet.com/category/job-role/planningmonitoring-scheduling
[5] http://www.planningplanet.com/category/industry/railway
[6] http://www.planningplanet.com/category/skills-expertise/scheduling-monitoring-%E2%80%A2-conversant-scheduling-primavera-p20-p30-p31-p5-p60
[7] http://www.planningplanet.com/category/skills-expertise/specialized-project-planning
[8] http://www.planningplanet.com/category/region/middle-east-region/asia/qatar-asqa