Dear friends
Please advise about your comments for the below mentioned secnario
Example as per Tender Drawings the Qty of foundation Concrete is 100 cum , while in the BOQ by Mistake its mentioned as 50 cum.
Now there has been changes and qty as per new drawings is 120 cum ,
Please advise what would be the qty considered for variation
Option #1 - Using BOQ Qty = 120-50 = 70 Cum
Option # 2 - Unsing Qty as per Tender = 120-100 = 20 cum
Please give your feedback
Thanks