Hi All,
Whilst I'm sure this topic has been consistently repeated, I would like to ask this again as I have yet been able to find a resolution:
Background:
I am currently in the midst of doing a rebaseline with revised contractual milestone dates
Key Notes:
1. Resources loaded on LOEs
2. No Negative Floats on all activities
3. Resource Curves applied on some of the resources
Observations:
1. Late start for LOE activities earlier than Data Date (Same as Actual Dates) for started activities
2. Remaining Late Units start before data date
3. Late Resource Curve above Early Resource Curve
I would like to seek your advice on how to resolve this so as to have the remaining late curve below the remaining early curve where it is supposed to be.
Regards,
Benjamin