I was trying to check an activity's resource distribution from Resource Assignments tab but eventually I realised that eventhough I increased the remaining time of that activity, the distribution of resource doesn't change. It only shows exact total cost of that activity for data date month.
Before performing the increase of remaining dates, there were only 5 days left for this activity but than another assumption came up and i had to increase it for 200 days. and now even if i recalculate assignment costs, that doesn't make any change. Program thinks we will spend all the units on the data date month.
How can I fix this problem and distribute the resources again according to remaining 200 days instead of previous assumption days which is 5 days.
Thanks in advance.