Hi all,
I was just asked to cost load P6 for a project that has been running already for 3 years..30,000+ activities..
I started by assigning in a cash resource the remaining $ (Contract BOQ $ - Actual to Date $) for each activity and the % is calculated based on site progress %, however this is way too time consuming.
The manpower is minimal for this task, any ideas on how to approach this task?