Hi,
Is there any way in P6 to show the milestones and their corresponding costs in P6 ? In short, am not sure if possible in activity view/gantt chart or Resource Assignment to show together the Milestones and their costs. I've tried to show them in Resource Assignment but the milestone dates are not showing. Note that the required cumulative cost should be cumulative.
If we could show both milestones and costs in one view only, then we can track easily the equivalent cost for each milestone. I've done thru excel by extracting the cumulative cos in Resource Assignment and the Milestone dates from the activity view of course. Just want only to check if possible in P6.
Greatly appreciated if you could help. Many thanks.