Hello,
I'm assigning resources to activities on my plan and as the project has not started yet I would expect the remaining units to be the same as the budgeted units. So basically if I have a 5 day duration activity and the resource will work 20 hours against that activity I change the budgeted units to 20 but the remaining units calculates to 40 hours.
Is there an easy way to change this so budgeted units and remaining units are the same?
Thanks