Dear All,
May be it seems stupid to ask this question but still i will prefer to ask.
In construction schedules, most of the activities go parallel. What logic do you people prefer while doing your schedule.
It is very difficult to make whole schedule or major part of schedule with Finish to start logic.
When we apply start to start + lag or finish to finish +lag, then still there will be open ends either at the start or at the end of activities. There is possibility to add some links to close them but those links will not be logical.
I am just wondering what is right relationship between the activities which are to be planned parallel without leaving any open end.
Best Regards