While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press schedule, the actual units go back to the earlier value instead of showing the updated value. Does anyone know why this happens?