I am reviewing a P6 scheule and noticed that I have several activities that are not on the critical path (red bars on the gnatt chart), but are calculating the same Total Float as activiites on the critical path. If the activities have the same Total Float does that make them all fall on the critical path? Can anyone shed a light on why this is occring?