Hi;
Can anyone help with the following.
My previous actual units changes everytime I update (Schedule Project). I'm Sure I Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes" at project level.
note:- the actual changes to be linear change (for ex. if actual units are 24 for 4 periods each period changes to be 6 units)