Hi everyone,
I was updating the progress. Wanted to extract actual & remaining labour units from primavera P6 R8.2in order to create Actual & Forecast curves.
I checked the forums, tried some options like:
- Negative Float - I have none
- Constraints - There are no constraints in the schedule, there is one Project constraint where you have to put Must Finish by x date. That comes after couple of months Early Finish Date.
My schedule still has Cumulative Remaining Late Units.
What do I do? Any advice would be appreciated.