Hello,
I am using P6 Version 8.4. I've been noticing that my finish dates are unactualizing (the 100% stays but the finish date pushes out to the current data date) - just wondering if anyone else has had this problem and how they fixed it. I've had to revise some of the quantities (material units and labour units) I'm not sure if this would have anything to do with it.
Any help would be greatly appreciated.