I have 02 separate projects, Client Engineering schedule and construction schedule, I wish to link relationships between 02 projects.
If I do assigning manual relationship by selecting project, “it Works” and it consumes more time. But If I try to import activity relationships between projects , “it fails” and am getting error note as below.
Excel Import log started : 21-Jun-16
INFO: Importing Global Data...
INFO: Importing Project Data...
INFO: Importing:
WARNING: TASKPRED: Failed to resolve foreign key for field Activity ID with value A2EC0850. Field cleared.
INFO: Saving:
ERROR: pred_proj_id is null for TASKPRED: toString invalid state
INFO: Saving Data to Database...
INFO: Deleting Unreferenced Data...
Kindly advise in this regard.
Regards,
Syed