We have a project with a requirement to maintain x number of parking spaces throughout. There are many activities that add and remove parking spaces.
I have found that in Layout: Activity Resource Assignments I can sort of get a spreadsheet showing the daily parking counts, but there are exceptions.
The goal is a printout with a gannt chart schedule above, and a total of the available parking spaces below. Is this possible?
I started with a simple schedule, and added LOE activities to create activities to assign the baseline quantities of spaces we started with. I defined the parking spaces as a resource. For each activity, in the Units/time field, I inserted either the number of spaces the activity adds or removes. In the Project/Resource Assignments view (which I have never previously used), I found the finish dates for the activies are very different than on the Project/Activities view, which causes the total number of spaces at any point in time to be incorrect.
Any direction on the best way to go about this, or links on documents to read would be greatly appreciated.
I am using Primavera Contractor, which as we understand is P6 limited to 2k activities.