Hello,
I have just made my way into a precast production company as a project planner. My role is to plan the erection process at site. That is I have to plan which elements are to be erected on which dates and so on and my company wants me to do it in primavera itself.
I make the schedule considering each element as an activity and connect them with FS relationship. But the issue is once I have prepared my plan, sometimes due to external issues the erection does not go in the order which I want. Basically my activities have no proper order of execution. Order doesn't matter. Which is making it very difficult for me to plan in primavera. Any suggestions will be very useful for me.
Regards
Mohamed