This may be a simple question but why if a task has a 1 day duration (8 hous) is the finish day the next day, e.g.
Start day - 4/13/2016 - duration 1 day == finish day is 4/14/2016. Logic tells me that the finish day is 4/13/2016.
Is there a way to show the real finish day without changine the duration to 0?