hey there,
i face a problem while i'm importing update to the baseline, the progress percentage for all activities wasn't the same in site so i changed all Performance % Complete, Start date and Finish date for all activities, there were some activities in the site completed and in the Xer file is still have % or with Zero %...and some activties percentages got increased and some got decreased...
when i prepared the Excel sheet and import it to baseline to re-update everything from the begining, the baseline didn't change and everything still Zero.
anyone have a solution for this problem ??
Regards,