Hi,
We have a planned shutdown in 2018 and our max amount of resources will be ~50. We will have a day and night shift but there will be a different amount of direct labour per shift. The ratio maybe 30 direct on days and 20 on nights. I will be assuming 9 productive hours per shift. And now for my question. Because I have an uneven amount of labour per shift, will my calendar be 18 hours productive out of 24? Should I be using a lesser productivity during the night?
Thanks