Does anyone have any advice on what I should in a situation where I am undertaking a windows analysis and the resulting delay is longer than the duraiton of the window itself? It seems a bit counterintuitive that for example I am showing a 60 day delay in a 30 day window.
What is considered "best practice" in these situations?