Dear Planners,
While analysing my project; the Scheduled % and Performance % values are not being shown in the WBS level and are only reflected for the activities. The schedule does not have any costs,resources or units assigned to it.
I need to compare the Current Progress with the Planned progress.
Please Help.
-Prateek