Hi all, I'm developing a baseline and I'm seeing TF in decimals (example 10.5) for activities assigned with one particular calendar(6 day workweek, 20h/day, 02:00 to 22:00). My other calendars are: 7 day workweek, 10h/day, 12:00 to 22:00 and 5 day workweek, 10h/day, 12:00 to 22:00. Data date is start of first acitvity 3 Feb 2016, 12:00 because this activity is assigned with the 3rd calendar(5 day workweek, 10h/day, 12:00 to 22:00). Am I missing something? Thanks.