I am creating a baseline with all FS relationships. The activities have been assigned with a 20hr/day, 6 day work week. I am noticing that all the activities have the start dates of their predecessors' finish dates. ie, the successor is starting on the same day the predecessor finishes. Anyone knows whats going on here?