Hello All,
Does anyone know how to show planned% complete on the bar graph for the dashboard report (project overview). The graph shows % complete (actual % complete) but I want to compare the planned% complete and actual% complete on that graph. Any suggestions?
P.S. The report is being generated with MS Project 2013.