Need some advise on how to create this report.
Here is the issue in the specifications.
"Using a SS, FF, or FS in unison as a predecessor or successor to an activity is prohibited."
Example: Activity 1000 has activity 1100 as a successor with both a FS and FF relationship type to activity 1000.
I have been working on this by using report writer to come up with a report to show where this is happening in the schedule without any success.
Any suggestions out there?
Thanks,
James B.