Hi All!
I am working on a Client side, I have a project scenario as below.
1. In our project, the conditions of contract states that Contractor cannot proceed without the approval of V.O.
2. Site Instructions has issued to Contractor before the approval of V.O. and on actual Contractor started V.O. works on site before the V.O. was approved by Client.
Now my question is, in analyzing delays using any method or TIA, what date must be used by us as a Client? Is it the date the V.O. was approved or is it the date Contractor has started on site based on the procurement and delivery dates?
Thanks in advance!