Hello PPlanners,
I try to import budgeted labor / non labor units from an Excel spreadsheet. In this spreadsheet, the units are not correlated to the activity durations. For instance, Non-labor resource A assigned to a 2-day long activity will be budgeted for 40 hours.
P6 recomputes the budgeted units to 16 hours.
The same applies to labor resources.
I am wondering how to set-up the project / activities / resources to be able to import my Excel values into the P6 project.
Thank you for your help,
Alexandre
P.S. I am sure Raphael will be of advice!