Hi,
I have been posted to another project site and that is supposed to finish by 31 Dec this year. And have some strange result of man-hour report in the programme. The Remaining Late Units man-hors finishing 19 weeks (Nov 2016) earlier then the Remaining Early Units man-hours at the data date April 2016. The project finish date has projected up to Aug 2016. I couldn’t understand that, if anyone can explain me how / why this happens.
Cheers Tanveer