Hi,
In an already existing program, I tried to give a finish date for an activity.
However, it takes start date as finish date.
Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100
HOwever,in the resources, there seem to be remaining units still left out instead of zero.
Kindly advise.
Thanks