Hello, All
Please help me with my below query:
In User preference my time units for time is set in days.
Activity A is having original duration of 28 days. This activity requires 24 technician perday for 28 days. So when i assign the technicain resource the budgeted units should be 24. ( bcoz the time units is set in day it will show 24d) .
Is this the right way ?
With above data when i see a histogram on resource usage profile with month as time scale do i need to take average?
Thank you guys for your help. Appreciate it.