The consultant requirement is to show in P6 “ % achieved “ with respect to duration and not accepting resource based “ % achieved ”. The illustration of requirement by Consultant shown below. Can any one guide, how we can make ready in P6. Is it right measure to track project progress?
Sl No | Activity Name | Duration | Duration Weightage | % progress complete | % Achieved |
| WBS | 140 | 100.0% | 8.60% |
|
1 | Activity -1 | 20 | 14.3% | 10% | 1.4% |
2 | Activity -2 | 50 | 35.7% | 20% | 7.1% |
3 | Activity -3 | 60 | 42.9% |
| 0.0% |
4 | Activity -4 | 10 | 7.1% |
| 0.0% |