I am working on a NEC3 project which has gone several months without having an accepted programme.
What is correct way to assess a compensation event in the period where there is not an accepted programme?
For example the last accepted programme is January and the event occurs at the start of June. Should progress from the End May rejected programme be added to the January programme to give a more realistic position at the time of the event. At the moment if the January programme is used the event is overstated.
I guess the question is also; if progress is added to an accepted programme is the programme still accepted?
Opinion here is divided.
Any views?